Projects
/ EcoGrid battery storage

EcoGrid battery storage

A 60 MW / 240 MWh battery co-located with an existing wind farm, using spare connection capacity to firm output.
EcoGrid battery storage
Southern Grid Cooperative
2024
Mid North, South Australia
Distribution scale storage
Let’s build a sustainable future together
Ask for the complete project report: objectives, implementation, measured results and the sustainability impact behind each figure.

The adjacent wind farm was being curtailed for roughly nine percent of its annual generation, partly by network constraint and partly by negative pricing in the middle of the day. Curtailed energy is free energy if you have somewhere to put it.

Co-location arithmetic

Sharing a connection point is what makes a project like this work. The wind farm rarely exports at full capacity, so the headroom is available for the battery to charge without a connection upgrade — and the battery can export into the same headroom when the wind is low, which is precisely when prices are high.

The constraint is the controls. A hybrid plant has to present a single set point to the network operator while internally deciding how to split it, and it has to do so within the operator’s telemetry and response requirements. That integration work was the technical heart of the project.

Delivery in fourteen months

  • Connection reassessment rather than a new application, saving an estimated eighteen months
  • Containerized system delivered in eleven shipments, with spacing set by the fire study
  • Hybrid controller commissioned against a hardware-in-the-loop model before energization
  • Market registration completed in parallel with construction

Co-location is the fastest storage you will ever build, because the hardest permission has already been granted.

First-year results

Forty-one percent of what had previously been curtailed is now captured and shifted. The battery also earns from frequency control services, which in this market pays well during the dispatch intervals immediately after a large unit trips.

Southern Grid Cooperative’s members see the combined plant’s revenue rather than the battery’s in isolation, which is the correct framing: the asset exists to make the wind farm worth more.

The hybrid controller has since been re-tuned twice as market dispatch rules changed, and the model it was commissioned against is maintained so that future changes can be tested before they reach the plant.

Firming a feeder that
ends a hundred kilometers out

Problem
  • Voltage excursions from rooftop solar already at the limit of the feeder's tolerance
  • Summer ambient temperatures above the standard thermal derating band
  • No permanent site presence within two hours of the installation
Challenge
A rural network with more solar than its own feeder could absorb
Solution
A distribution-connected battery specified for ambient rather than datasheet conditions
Why this matters
Specifying thermal management for a 47 degree ambient rather than the datasheet's 35 added cost and removed the derating that would have cut summer throughput by a fifth.
Designing for remote operation from the start meant the nearest technician being two hours away became a maintenance schedule rather than an availability risk.

Fourteen months from
voltage study to dispatch

Q1 2023
Network study
A full year of feeder voltage and power-quality data against every connected solar system.
Q2 2023
Specification
Thermal design set to measured ambient extremes, and remote operation made a design requirement.
Q3 2023
Consent
Council approval and the network connection agreement signed with the distribution operator.
Q4 2023
Construction
Pad, containers and the 33 kV connection built inside a single dry season.
Q1 2024
Operation
Voltage excursions down 94% at the feeder end, with the asset dispatching on network signals.