Projects
/ North sea wind array

North sea wind array

A 400 MW offshore wind array built on monopile foundations, with a construction schedule set backward from vessel availability.
North sea wind array
Nordlys Energi
2026
North Sea, offshore Denmark
Offshore wind
Let’s build a sustainable future together
Ask for the complete project report: objectives, implementation, measured results and the sustainability impact behind each figure.

Nordlys Energi held a seabed lease and a grid connection offer with an expiry date. The project had been through two feasibility studies without reaching a financial investment decision, largely because the installation schedule had never been tested against what vessels were actually available.

The scheduling problem

We rebuilt the program backward from the heavy-lift vessel market rather than forward from a desired commercial operation date. That single change moved foundation installation a full season earlier and removed a weather-window assumption that would not have survived a normal winter.

Everything else became float. Cable manufacture, onshore substation works and turbine delivery were all sequenced against the two fixed offshore campaigns, and penalties in the supply contracts were aligned to those dates rather than to the overall completion date.

Engineering decisions

  • Monopiles rather than jackets, after geotechnical work confirmed competent sand throughout the array area
  • A 66 kV array voltage, cutting cable losses and reducing the number of strings
  • Scour protection sized from a two-year current and wave record, not a regional model
  • Noise mitigation during piling, with marine mammal observation across the full campaign

The array cable route was moved 900 meters to avoid a designated sandbank. That detour cost four million euros and removed the largest single consenting risk on the project.

Outcome

First power came seven weeks ahead of the contractual date, and the array reached full commercial operation within the same construction season. Measured capacity factor across the first twelve months is forty-eight percent, half a point above the P50 forecast.

Nordlys now operates the array with an availability-linked service agreement and an independent condition monitoring feed, which has already supported two gearbox warranty claims on the operator’s own data.

The measurement record and the geotechnical dataset assembled during development remain the project’s most durable asset, and both are already being reused in the feasibility work for an adjacent lease area.

An offshore build with
a fixed weather window

Problem
  • Installation vessel availability booked eighteen months ahead across the whole North Sea
  • Unexploded ordnance survey returning more contacts than the baseline assumed
  • Export cable landfall through a protected dune system
Challenge
A first offshore project for a developer with an onshore track record
Solution
Vessel slots secured before consent, and landfall moved to directional drilling
Why this matters
Booking installation vessels before consent was granted carried real risk, and it is the only reason the 2026 weather window was met.
Drilling under the dune system rather than trenching through it cost more and removed the objection that would have delayed landfall by a season.

Forty-six months from
lease award to first power

Q1 2022
Site survey
Geophysical and geotechnical campaign, plus a UXO survey that returned 214 contacts across the array.
Q3 2023
Consent
Environmental statement accepted, with landfall re-routed to a drilled crossing under the dunes.
Q1 2024
Procurement
Turbine supply, foundation fabrication and two installation vessel slots contracted in one package.
Q2 2025
Installation
Monopiles, array cabling and the offshore substation placed inside a single summer window.
Q4 2026
Operation
First power to the Danish grid, with commissioning closed out ahead of the winter shutdown.